go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_SHET_0034
Title Low Profile 132kV Steel Poles
Status Completed
Energy Categories Other Power and Storage Technologies(Electricity transmission and distribution) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
SSEN Scottish Hydro Electric Transmission
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 January 2022
End Date 31 July 2023
Duration ENA months
Total Grant Value £1,650,000
Industrial Sectors Power
Region Scotland
Programme Network Innovation Allowance
 
Investigators Principal Investigator Project Contact , SSEN Scottish Hydro Electric Transmission (100.000%)
  Industrial Collaborator Project Contact , Scottish and Southern Energy plc (0.000%)
Web Site https://smarter.energynetworks.org/projects/NIA_SHET_0034
Objectives Steel alternatives to the wood poles used for trident wood pole construction are required to provide an equivalent solution for the construction of non-resilient overhead lines (OHLs) at altitudes above 300m, where wood poles are impractical, and to provide an alternative supply chain to address the long lead times and creosote obsolescence risk associated with wood poles.Lessons learned during deployments of a composite pole OHL on its transmission network to connect the Dorenell wind farm, and the NeSTS trial OHL at Quoich, are available to inform this work. The most critical of these are that prototypes are utilised at full scale by SSEN and its contractors before the design is frozen, that no accessories requiring frequent inspection are designed to remain mounted to structures, and that the designs are readily manufacturable by multiple companies in response to fully detailed drawings.OHLs constructed with the new steel supports must meet the internal requirements defined for wood poles, and the functional requirements detailed in NeSTS Low Profile 132kV SC Functional Requirements. The project will be split into three work packages to –1. Develop prototype designs.2. Build prototypes and report on performance and subsequent design refinement.3. Conduct type testing for Technical Authority approval. The project objective is to create a low-profile design which replicates the visual consenting envelope, reliability levels, insulation level, and construction methods associated with wood poles, significantly reducing future construction costs. Application of the low-profile design within the existing design suite as a substitute for current steel structures could provide a significant reduction in construction costs to the year ending 2026. Lower construction costs will provide customers with lower cost connections and support energy system transition.
Abstract Steel alternatives to the wood poles used for trident wood pole construction are required to provide an equivalent solution for the construction of non-resilient overhead lines (OHLs) at altitudes above 300m, where wood poles are impractical, and to provide an alternative supply chain to address the long lead times and creosote obsolescence risk associated with wood poles.
Publications (none)
Final Report (none)
Added to Database 26/10/22